Project Updates

Nov 15, 2023

Project Highlights

Project Highlights
• Sam Houston Electric Cooperative - $54 Million
138KV NEW FRED SUBSTATION - $6.2 Million
138KV NEW FRED-WARREN OVERHEAD TRANSMISSION LINE - $13.9 Million

WOODVILLE 138KV NEW FRED-FORK CREEK OVERHEAD TRANSMISSION LINE - $34 Million


Sam Houston Electric Cooperative (SHECO) and Power Engineers Incorporated (Consultant) continue
Permitting through AFE Approval 2Q24 (Apr). Upon Approval, Sam Houston Electric expects to release
RFPs for General Contractor 1Q24 (Mar). Selected General Contractor will conduct Engineering and
release RFQs and Bid Documents for Equipment 2Q24 (Jun). Consumables plus Subcontractors as
required 4Q24 (Dec). Construction is scheduled for Kick-Off 3Q24 (Sep). Project completion is
expected 4Q25 (Oct).

DEWEYVILLE NATURAL GAS 336MW COTTONWOOD UNIT 03 4Q24 MAINTENANCE OUTAGE - $12.5 Million
MAJOR TURBINE INSPECTION AND REPAIR: GE Power 7F.04 7FA.03 MS7001FA+e Heavy Frame Combustion
Turbine with (1) Wood Foster Wheeler Triple Pressure Duct Fired LNB SCR (824/855/24KPPH) 1,687,000
lbs/hr 2,010 PSIG 1,055 deg F and (1) 137MW GE ALSTOM Heritage Condensing Heavy Frame Combustion
Turbine. Cleco Cajun LLC continues Maintenance Planning & Scheduling through AFE approval 1Q24 and
will release RFQ's with Bid Documents for Equipment, Consumables and Specialty Subcontractors as
required 2Q24 (Apr) thru 3Q24 (Jul). Maintenance Outage is scheduled to kickoff 4Q24 (Oct) and is
expected to be completed by 4Q24 (Nov)

WESTLAKE NATURAL GAS 826MW LAKE CHARLES POWER BLOCK #01 1Q24 MAINTENANCE OUTAGE - $2.8 Million
ANNUAL INSPECTIONS AND REPAIRS TO: (2) 276MW Mitsubishi Hitachi Power Systems M501G Heavy Frame
Combustion Turbine with (2) Nooter/Eriksen Heat Recovery Steam Generator (HRSG) and (1) 274MW
Toshiba Energy Systems & Solutions Corporation Steam Turbine. Entergy Gulf States Louisiana LLC
continues Maintenance Planning & Scheduling through AFE approval 3Q23 (Jul) and will release RFQs
with Bid Documents for Equipment, Consumables and specialty Subcontractors as required 4Q23 (Oct)
thru 4Q23 (Dec). 826MW Natural-Gas Combined Cycle Unit #01 17-Day Maintenance Outage is scheduled
to kickoff 1Q24
(Mar) and is expected to be completed by 1Q24 (Mar).